RAWYA FARMS DEVELOPMENT - Updated Docs

Rawya Farms

Justin Jones from Insite Engineering attended the Planning and Zoning regular meeting on November 20th, 2023 to provide an update on changes made to the proposed Rawya Farms development.

Mr. Jones shared information that has been requested by the board and obtained as it pertains to Rawya Farms. Mr. Jones presented an updated master plan which shows the removal of 82 wooded acres at the eastern end of the property that is adjacent to Deerwood Lake Community. Parcel ID 07 418 0 000 050.000 will retain its existing zoning as A-1.

It was discussed that 3 acres will be donated to the Town for a future fire/safety facility. There has been a reduction from 1,086 residential lots to 977 as well as the removal of 12 acres for the commercial building.

Click the link below to review documents presented at this meeting.

https://www.dropbox.com/scl/fo/4jigkz9gpz28j4zv4isj3/h?rlkey=dhi6hwp97ba...